Production Plan

You’ll find this under Manufacturing → Production Plan.

A production plan brings demand from several orders into one place before work is released to the factory. It lets the planner check available stock and create the required manufacturing and purchasing documents together.

The plan shows what needs to be produced, what can be supplied from stock, and what still needs to be made or purchased.

A production plan does not move stock. It prepares the demand and creates the documents that will do the work later: work orders, job cards, purchase requests, and subcontracting orders.

When a plan is useful

A production plan is useful when several orders need the same materials or machines, an item has sub-assemblies made in-house, or purchasing needs one shortage list. For a small one-off run, it may be quicker to create a work order directly.

Before you begin

Check these first. Most problems in a plan begin in one of these records.

  • The finished items have active, submitted BOMs.
  • Sub-assemblies have their own BOMs if you intend to make them in-house.
  • Current stock balances and item units are correct.
  • Workstation types, operation times, and capacities are realistic if you will use Capacity Planning.

Creating a production plan

Start a new plan

Open Manufacturing → Production Plan, select New, and give the plan a recognisable name. A name such as “September Retail Orders, Week 2” will be more useful later than “Plan 4”. Set the posting date and add a short description when the plan covers a special campaign or deadline.

Bring in the demand

Select Get Items to choose sales orders. ERPX brings eligible lines into Items to Manufacture. You can also add an item manually when the run is for replenishment rather than a customer order.

Review the finished items

For each line, confirm the BOM, planned quantity, stock quantity to use, order quantity, and tolerance. The imported sales-order quantity is a starting point. Adjust it for practical batch sizes and confirm how much available stock should be used.

Load the sub-assemblies

Open Sub Assembly Items and select Get Sub Assemblies. ERPX expands the BOMs and shows the intermediate items needed by the finished goods. Choose whether each one will be made In House or Subcontracted, and review the stock utilisation before accepting the order quantity.

Calculate the raw material requirement

Open Material Request Items and select Get Raw Materials. This is the consolidated shortage after the BOM requirements and available stock have been considered. Review it before creating any purchase request; a wrong stock quantity here becomes unnecessary buying later.

Save the draft

Create the plan and read it once in view mode. The summary should agree with the sales orders, and every item to manufacture should have the BOM you expected.

Approve when the demand is settled

Approval makes the plan actionable. Once approved, use Create to generate work orders, job cards, purchase requests, or subcontracting orders from the plan.

What each tab is for

TabWhat to check
DetailsPlan name, posting date, description, accounting dimensions, and the overall quantity summary
Sales OrdersWhich customer orders supplied the demand
Items to ManufactureFinished items, BOMs, planned quantity, stock utilisation, quantity ordered, quantity produced, and what remains
Sub Assembly ItemsIntermediate items, BOM level, stock used, order quantity, tolerance, and in-house or subcontracted method
Material Request ItemsRaw material required, stock used, quantity requested, and quantity received
Work OrdersManufacturing work created from this plan and its progress
Subcontracting OrdersOutsourced work created from this plan
Print CardsPrintable plan cards for floor use
Cost BreakdownPlanned cost and linked manufacturing cost; visible to manufacturing administrators

If a quantity looks unexpected, open the Material Explosion View under the manufactured item. It shows the raw materials and operations behind that line so you can trace how ERPX calculated the total.

Planning options

OptionUse it when
Include Non-Stock ItemsA BOM contains services or other non-stock lines that still belong in the requirement
Include Subcontracted ItemsOutsourced sub-assemblies should remain visible in the plan
Consider Minimum Order QtyPurchasing or production should respect the item’s minimum lot size

These switches change the requirement. If two planners get different numbers from the same sales orders, compare these settings before checking the BOMs.

Status and actions

StatusWhat it meansTypical next action
DraftStill being preparedEdit, approve, or cancel
ApprovedDemand is confirmedCreate the required documents
Material RequestedAt least one purchase request has been createdFollow purchasing and begin available work
In ProcessLinked manufacturing work has startedMonitor work orders and the schedule
ClosedPlanning work is finished and archivedReopen only when more planning work is required
CancelledThe plan was withdrawnNo further production should be created from it

Closing a plan does not cancel its work orders or purchase requests. It closes the planning record; linked documents keep their own status and must be managed where they were created.

Scheduling from the plan

Once work orders and job cards exist, Edit Schedule lets you adjust their planned dates in bulk. If you need to see whether the dates are actually possible across all machines, use Capacity Planning. The production plan says what you intend to make; capacity planning tests when the factory can make it.

Choose the PDF that suits the people who will use it:

  • Production Plan PDF gives the overall plan and quantities.
  • Planned Schedule PDF records the dates you set.
  • Expected Schedule PDF reflects the calculated production timing.
  • Cost Breakdown PDF is the commercial view and should be shared only with users who are meant to see rates and costs.

Common problems

What you seeLikely reasonWhat to do
A sales-order item was not importedIt has no submitted BOM or is not a manufacturing itemCheck the item and BOM, then run Get Items again
Get Items says there are no new itemsEvery eligible line is already in the planReview the existing Items to Manufacture tab
Sub-assemblies are missingThey have not been loaded, or the parent BOM does not mark them as BOM itemsCheck the parent BOM and use Get Sub Assemblies
Raw material looks too highStock utilisation is zero, safety stock is included, or the BOM quantity is wrongCheck the plan options, stock, and BOM batch quantity
Raw material looks too lowNon-stock or subcontracted items were excluded, or stock was overstatedReview the inclusion switches and stock quantity
Work order cannot be createdThe plan is still Draft, the BOM is unavailable, or the line has no remaining order quantityApprove the plan and review the affected item
A purchase request already exists for part of a lineThe Requested Qty column records earlier requestsCreate only the remaining shortage

Final check

Before approving, check one finished item all the way through. Compare the sales quantity, available finished stock, sub-assemblies, raw materials, and selected BOM. This usually catches unit and batch-size mistakes before they affect every line in the plan.